border

[Technic] Slow Gateway Orders

cwilson at cardinals.k12.mo.us cwilson at cardinals.k12.mo.us
Thu Aug 2 09:13:53 CDT 2007


We ordered 88 in May.  I've heard a batch of promises but no results.  I 
did a first and sold my old machines in May not expecting any problem.  
I also was told that I was upgraded to try to speed them up.  I'm really 
getting nervous as I'm down to two weeks before school starts.  I 
ordered XP Pro.  The relocation seems to be the issue.  I was told Tues 
that I could cancel the order but it's to late now and I've been Gateway 
twelve years. I knew it would be awhile when I ordered but was told July 
6th when I ordered.  Chuck

Bill Talley wrote:
> Anyone else have major delays with their Gateway computer orders??? 
>
> Wonder if Vista is causing the delays...
>
> They called me yesterday and said that they were upgrading the motherboard at no 
> extra cost which has an intel nic and blah, blah, blah, and we are sorry it is taking so 
> long...were upgrading you so maybe they will move faster... WHAT ?!?!?! 
>
> Did I hear correctly a few months ago that they had build a new facility or 
> something??? I'm about to come to the conclusion that Vista is causing them 
> problems...I ordered these with Vista License but of course I will downgrade them to 
> XP when they get here....IF THEY EVER DO GET HERE!!!
>
> Whooooow... Okay, I can go back to work now... :-)
>  
>
>
>
> Bill Talley
> Gainesville R5
> HC 3 Box 170
> Gainesville, MO. 65655
>
> Voice: 417-679-4200
> FAX: 417-679-4270
>
>
> _______________________________________________
> Technic mailing list
> Technic at lists.more.net
> http://lists.more.net/mailman/listinfo/technic
>   

-- 
Chuck Wilson
Technology Coordinator
4154 Highway 36
Shelbina, MO. 63468
cwilson at cardinals.k12.mo.us
Off # 573-588-2618